News release: “The Nuclear Regulatory Commission has concluded its mandatory hearing on Southern Nuclear Operating Companys (SNC) application for two Combined Licenses (COL) at the Vogtle site in Georgia. In a 4-1 vote, the Commission found the staffs review adequate to make the necessary regulatory safety and environmental findings, clearing the way for the NRCs Office of New Reactors to issue the COLs. The Commission imposed a condition on the COLs requiring inspection and testing of squib valves, important components of the new reactors passive cooling system. The NRC staff is expected to issue the COLs within 10 business days. The COLs will authorize SNC to build and operate two AP1000 reactors at the Vogtle site, adjacent to the companys existing reactors approximately 26 miles southeast of Augusta, Ga. NRC construction inspectors have been on-site since April 2010, examining SNCs activities to prepare the plants foundation under a Limited Work Authorization the NRC issued on Aug. 26, 2009.”