Department of Homeland Security – FPS’ Exercise of a Contract Option for the Risk Assessment and Management Program, 03/27/12, OIG-12-67
Assess and analyze risk posed to federal facilities and mitigate those risks by recommending and tracking countermeasures; and
Manage post inspections, guard contracts, and individual guard certification compliance.
In July 2011, the Government Accountability Office (GAO) reported that RAMP was over budget, behind schedule, and could not be used as intended. According to the GAO report, several factors contributed to RAMP deficiencies. Specifically, FPS changed the original requirements, which caused the contractor to add additional resources; FPS did not conduct user testing as part of development; and ICE did not complete contractor performance evaluations.”